How do I install a GDQX-500 rebar shearing line?
Installation follows four steps: a level foundation sized for the 28243 × 2545 × 1800 mm line, a 47.8 kW power supply at 380 V / 50 Hz, hydraulic oil and air connections, then commissioning and a test run with your bar sizes. Allow clearance for 12 m stock on the infeed and for cut-bar removal on the outfeed. We confirm the foundation drawing, utility list and commissioning schedule with the order; the exact site time depends on the foundation and utilities being ready.